SEKFORDE STREET
Location – Farringdon, London
Client – Fletcher King
Contract Sum – £1,500,000
Completion Date – January 2018

The creation of a new office spaces over 4 floors. Works involved creation of new office units which included:
- New floor added to the roof.
- Full strip out.
- Complete replacement of the Mechanical and electrical services.
- Formation of new lift shafts and openings in structural floors.
- Refurbishment of all fixtures and fittings.
- Refurbishment of existing facades.
- New glazing package.
- Replacement of floor coverings and Decoration throughout.
- Creations of new WC and Kitchen on each floor


PLANTAIN PLACE
Location – London
Client – ADP Architecture
Contract Sum – £1,100,000
Completion Date – May 2016

The creation of a new office spaces over 3 floors with residential above. Works involved creation of new office units which included:
- Full strip out.
- Complete replacement of the Mechanical and electrical services.
- New roof coverings with a additional floor added.
- Replacement of suspended ceilings.
- Supply and installation of new signage.
- Refurbishment of all fixtures and fittings.
- Decoration throughout.


LLOYDS COURT SHOPPING CENTRE MANAGEMENT SUITE
Location – Lloyds Court, Milton Keynes
Client – Palatium Investment Management Ltd
Contract Sum – £155,000 part of £7,000,000 Project
Completion Date – July 2019

The refurbishment and redevelopment of Lloyds Court Shopping centre in
Central Milton Keynes. The scheme when finished will provide 11,258 m² of
retail and restaurant units. which included:
- Full strip out of internal finishes back to shell
- Asbestos removal in all areas
- Full refurbishment to the Landlords areas to install new LED Lighting
- Full revamp to the courtyard areas
- Fully fitted out modern Management Suite


TURNER & TOWNSEND
Location – Birmingham
Client – Turner & Townsend
Contract Sum – £115,000
Completion Date – January 2016

The project involved a full office refurbishment which included:
- Refurbishment of all fixtures and fittings
- Complete replacement of the Mechanical and electrical services
- New raised floor
- New glass partition
- Replacement of floor coverings
- Decoration throughout


ADP BIRMINGHAM
Location – Birmingham
Client – ADP Architecture
Contract Sum – £170,000
Completion Date – March 2019

The project involved a full office refurbishment which included:
- Refurbishment of all fixtures and fittings
- Complete replacement of the Mechanical and electrical services
- New raised floor
- New glass partition
- Additional secondary glassing throughout
- Creations of new WC and Kitchen
- Replacement of floor coverings
- Decoration throughout